Identify the missing words in the following sentence.

The 'starting up a project' process is triggered when a [ ? J is available.

A.
project business case
Answers
A.
project business case
B.
project mandate
Answers
B.
project mandate
C.
stage plan
Answers
C.
stage plan
D.
work package
Answers
D.
work package
Suggested answer: B

Explanation:

The 'Starting up a Project' process in PRINCE2 is typically triggered when a project mandate is available. The project mandate provides the basic information necessary to define whether there is sufficient justification to proceed with the project's setup.

Reference: PRINCE2 Foundation Manual