What is established during the 'initiating a project' process?

A.
The agreed protect acceptance criteria
Answers
A.
The agreed protect acceptance criteria
B.
The need for a configuration library
Answers
B.
The need for a configuration library
C.
A plan for the work or project initiation
Answers
C.
A plan for the work or project initiation
D.
An understanding of the project's funding
Answers
D.
An understanding of the project's funding
Suggested answer: C

Explanation:

During the 'Initiating a Project' process in PRINCE2, a detailed plan for the work needed for project initiation is established. This includes developing the various management strategies and the project initiation documentation (PID) that will guide the project's execution and control phases.

Reference: PRINCE2 Foundation Manual