Which is an objective of the 'controlling a stage' process?

A.
To review the business justification for the project
Answers
A.
To review the business justification for the project
B.
To replan the current stage when directed
Answers
B.
To replan the current stage when directed
C.
To develop products to defined quality criteria
Answers
C.
To develop products to defined quality criteria
D.
To produce a learn plan for the work package
Answers
D.
To produce a learn plan for the work package
Suggested answer: B

Explanation:

An objective of the 'Controlling a Stage' process in PRINCE2 is to replan the current stage when directed. This process handles day-to-day management of the project, and includes responding to issues that might impact the stage plan, requiring replanning to ensure project objectives can still be met.

Reference: PRINCE2 Foundation Manual