Question 347 - PRINCE2-7-Foundation discussion

Report
Export

How does product-based planning help to determine the project approach?

A.
By Identifying the outputs that the project trust deliver
Answers
A.
By Identifying the outputs that the project trust deliver
B.
By planning in detail how to deliver the outputs over a more predictable time scale
Answers
B.
By planning in detail how to deliver the outputs over a more predictable time scale
C.
By managing constraints to the planned completion date for the project
Answers
C.
By managing constraints to the planned completion date for the project
D.
By dividing the delivery of the project's outputs into stages which do not overlap
Answers
D.
By dividing the delivery of the project's outputs into stages which do not overlap
Suggested answer: A

Explanation:

Product-based planning in PRINCE2 focuses on defining and understanding the project's outputs or products. This method helps in determining the project's approach by clarifying what products must be delivered, thus guiding the planning of activities and resources needed to create these products. It ensures that the project's structure and execution strategy are aligned with delivering tangible, well-defined outcomes.

Reference: PRINCE2 7 Foundation resources on product-based planning.