Which plan should only be produced if the project is large and complex enough?

A.
Project plan
Answers
A.
Project plan
B.
Stags plan
Answers
B.
Stags plan
C.
Team plan
Answers
C.
Team plan
D.
Exception plan
Answers
D.
Exception plan
Suggested answer: C

Explanation:

In PRINCE2, a Team Plan is a type of plan that might only be produced for very large or complex projects. It is typically more detailed and is specifically designed to manage a segment of the project within a certain team or group. This plan provides detailed guidance on the delivery of the products assigned to the team within the constraints set by the Stage Plan.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)