Question 350 - PRINCE2-7-Foundation discussion
The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual products being worked on.
Which part of effective issue management is the project manager applying?
A.
Baselines
B.
Change budget
C.
Change control
D.
Issue resolution
Your answer: