The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management' technique should the project manager document this?

A.
Identify: define context and objectives
Answers
A.
Identify: define context and objectives
B.
Identify: identify threats and opportunities
Answers
B.
Identify: identify threats and opportunities
C.
Assess: prioritize risks
Answers
C.
Assess: prioritize risks
D.
Assess: combine risk profile
Answers
D.
Assess: combine risk profile
Suggested answer: A

Explanation:

The step where the project manager needs to document how risk management will be undertaken during the project is during the 'Identify: define context and objectives' step of the risk management technique. This initial step is crucial for setting the scope and objectives of risk management activities, providing a framework for identifying, assessing, and managing risks throughout the project.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)