Whitt is 3 purpose of the initiating a project' process?
A.
To prepare the contract for the project to enable the project board to commit to delivery
B.
To provide the project board with Just Enough Information to decide whether to approve the Initiation stage
C.
To provide the opportunity for the senior user in confirm that they find the project product acceptable
D.
To enable the project board to empower the project manager to work within delegated authority limits