According to the 'exception management' technique, when should the team manager raise an issue?

A.
When the team manager predicts that a product will cause a stage to exceed its time tolerance
Answers
A.
When the team manager predicts that a product will cause a stage to exceed its time tolerance
B.
When the team manager identifies that a product is going to be delivered late
Answers
B.
When the team manager identifies that a product is going to be delivered late
C.
when the team manager predicts that a product will cause a work package to exceed its time tolerance
Answers
C.
when the team manager predicts that a product will cause a work package to exceed its time tolerance
D.
when the team manager identifies that the work package has already exceeded its time tolerance
Answers
D.
when the team manager identifies that the work package has already exceeded its time tolerance
Suggested answer: C

Explanation:

According to the 'exception management' technique, the team manager should raise an issue when they predict that a product will cause a work package to exceed its time tolerance. This proactive approach allows for timely decision-making and corrective action by the Project Board, ensuring that project delivery is kept on track and within the agreed tolerances.

Reference: PRINCE2 methodology and exception management guidance.