Which TWO are objectives of the 'controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage's products meet-agreed quality expectations

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: D

Explanation:

The objectives of the 'Controlling a Stage' process in PRINCE2 include focusing on the completion of work within agreed tolerances and ensuring that all stage products meet the agreed quality expectations. These objectives are central to maintaining control over the stage and ensuring that the project delivers outputs that are fit for purpose.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation