Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?
A.
Increase the frequency of checkpoint reports
B.
Allow the team manager more flexibility to exceed cost tolerance
C.
Increase the frequency of event-driven controls
D.
Increase the frequency of escalations by the team manager
Your answer: