Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

A.
Increase the frequency of checkpoint reports
Answers
A.
Increase the frequency of checkpoint reports
B.
Allow the team manager more flexibility to exceed cost tolerance
Answers
B.
Allow the team manager more flexibility to exceed cost tolerance
C.
Increase the frequency of event-driven controls
Answers
C.
Increase the frequency of event-driven controls
D.
Increase the frequency of escalations by the team manager
Answers
D.
Increase the frequency of escalations by the team manager
Suggested answer: A

Explanation:

When a team manager is inexperienced, increasing the frequency of checkpoint reports can provide the project manager with more frequent updates on progress and issues. This allows for quicker identification and resolution of problems, thus maintaining better control over the project's progress and supporting the team manager more effectively.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation