The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

A.
Manage by stages
Answers
A.
Manage by stages
B.
Focus on products
Answers
B.
Focus on products
C.
Tailor to suit the project context
Answers
C.
Tailor to suit the project context
D.
Learn from experience
Answers
D.
Learn from experience
Suggested answer: C

Explanation:

The principle that the project manager is applying by reviewing changes in team dynamics is 'Tailor to suit the project context'. This principle involves adapting the management of the project to the environment, including the team dynamics, to ensure that the project management approach is appropriate for the specific context and challenges of the project.

Reference: PRINCE2 7 Foundation handbook and principles section.