Question 368 - PRINCE2-7-Foundation discussion
The project manager reviews whether there has been a Change in the way team members relate to each other.
Which principle is the project manager applying as part of the 'people' element?
A.
Manage by stages
B.
Focus on products
C.
Tailor to suit the project context
D.
Learn from experience