In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

A.
Preparing estimates
Answers
A.
Preparing estimates
B.
Defining and analyzing the products
Answers
B.
Defining and analyzing the products
C.
Organizing work packages
Answers
C.
Organizing work packages
D.
Preparing a schedule
Answers
D.
Preparing a schedule
Suggested answer: A

Explanation:

In the 'planning' technique, a team manager should break down the cost of delivering a work package during the 'Preparing estimates' step. This involves estimating the resources and time required to deliver each component of the work package, which are critical for budgeting and resource allocation.

Reference: PRINCE2 Foundation course material on planning techniques and project management documentation.