Question 370 - PRINCE2-7-Foundation discussion
Why is change management important in a project?
A.
It provides clarity on how the culture of an organization needs to adapt over time
B.
It provides processes and management products to use when requesting a change
C.
It provides confidence that the project can meet is objectives and has continued business Justification
D.
It provides a controlled and bidirectional flow of information to key Influencers