Question 370 - PRINCE2-7-Foundation discussion

Report
Export

Why is change management important in a project?

A.
It provides clarity on how the culture of an organization needs to adapt over time
Answers
A.
It provides clarity on how the culture of an organization needs to adapt over time
B.
It provides processes and management products to use when requesting a change
Answers
B.
It provides processes and management products to use when requesting a change
C.
It provides confidence that the project can meet is objectives and has continued business Justification
Answers
C.
It provides confidence that the project can meet is objectives and has continued business Justification
D.
It provides a controlled and bidirectional flow of information to key Influencers
Answers
D.
It provides a controlled and bidirectional flow of information to key Influencers
Suggested answer: B

Explanation:

Change management is important in a project because it provides structured processes and management products to manage and implement changes effectively. This ensures that all changes are assessed, approved, managed, and documented properly, helping the project adapt to changes while maintaining control and alignment with project objectives.

Reference: PRINCE2 Foundation official resources and training on change management.