Who is responsible for managing the progress of work during a Sprint?

A.
The Scrum Master.
Answers
A.
The Scrum Master.
B.
The Development Team.
Answers
B.
The Development Team.
C.
The Product Owner.
Answers
C.
The Product Owner.
D.
The most junior member of the Team.
Answers
D.
The most junior member of the Team.
Suggested answer: B