Question 179 - PSM I discussion
Which answer best describes the topics covered in Sprint Planning? (Choose the best answer.)
A.
What to do and who will do it.
B.
How conditions have changed and how the Product Backlog should evolve.
C.
What can be done and how to do it, and why to do it.
D.
What went wrong in the last Sprint and what to do differently this Sprint.
E.
Who is on the team and what team member roles will be.