A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product.

Which of the following charts would BEST prioritize which defects to address?

A.
Pareto
Answers
A.
Pareto
B.
Run
Answers
B.
Run
C.
Control
Answers
C.
Control
D.
Histogram
Answers
D.
Histogram
Suggested answer: A

Explanation:

The project manager should use a Pareto chart to prioritize which defects to address for the product.

A Pareto chart is a type of bar chart that shows the frequency or impact of different causes of problems or defects. It also shows a cumulative line that represents the percentage of the total frequency or impact. A Pareto chart can help to prioritize the causes that have the most significant effect on the quality of the product and apply the 80/20 rule, which states that 80% of the problems are caused by 20% of the causes.