Which of the following activities would a project manager perform during the closing phase? (Select

THREE).

A.
Lessons learned
Answers
A.
Lessons learned
B.
Risk analysis
Answers
B.
Risk analysis
C.
Removing resources
Answers
C.
Removing resources
D.
Acquiring resources
Answers
D.
Acquiring resources
E.
Statement of work sign-off
Answers
E.
Statement of work sign-off
F.
Stakeholder analysis
Answers
F.
Stakeholder analysis
G.
Removing access
Answers
G.
Removing access
Suggested answer: A, C, G

Explanation:

Lessons learned, removing resources, and removing access are activities that a project manager would perform during the closing phase of a project. Lessons learned is a process of collecting and documenting the knowledge and experience gained from a project for future reference and improvement. Removing resources is a process of releasing or reallocating any human or material resources that were used for the project. Removing access is a process of revoking any permissions or privileges that were granted to the project team members or stakeholders for accessing any systems or data related to the project. These activities can help to finalize and close a project successfully and ensure that all deliverables are transferred, all documentation is approved and archived, all contracts are closed, and all stakeholders are satisfied.