A project manager has been informed that the delivery of required IT equipment will be delayed.

Which of the following is the FIRST step the project manager should take?

A.
Make an impact assessment.
Answers
A.
Make an impact assessment.
B.
Prepare a new purchase order.
Answers
B.
Prepare a new purchase order.
C.
Select a new vendor.
Answers
C.
Select a new vendor.
D.
Create a risk register.
Answers
D.
Create a risk register.
Suggested answer: A

Explanation:

The project manager should make an impact assessment after being informed that the delivery of required IT equipment will be delayed. An impact assessment is a process of analyzing and evaluating how a change or an issue may affect the scope, schedule, cost, quality, or risks of a project. An impact assessment can help to determine the severity and implications of the delay on the project objectives and deliverables and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.