Question 61 - PK0-005 discussion
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
A.
Create a list of tasks and share it with the team.
B.
Resend the scope of work to the team.
C.
Review the Gantt chart weekly with the team.
D.
Have the project sponsor meet with the team.