A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

A.
Create a list of tasks and share it with the team.
Answers
A.
Create a list of tasks and share it with the team.
B.
Resend the scope of work to the team.
Answers
B.
Resend the scope of work to the team.
C.
Review the Gantt chart weekly with the team.
Answers
C.
Review the Gantt chart weekly with the team.
D.
Have the project sponsor meet with the team.
Answers
D.
Have the project sponsor meet with the team.
Suggested answer: C

Explanation:

Reviewing the Gantt chart weekly with the team would be the most effective step for the project manager to take to ensure clarity within the team after receiving feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. A Gantt chart is a graphical tool that shows the schedule of a project, including the start and end dates, durations, dependencies, milestones, and progress of each task or activity. Reviewing the Gantt chart weekly with the team can help to clarify their roles and responsibilities, assign tasks and deadlines, track and report their status and performance, identify and resolve any issues or risks, and keep them aligned and engaged with the project goals.VVVVVVVVVVVVVV