Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

A.
Memorandum of understanding
Answers
A.
Memorandum of understanding
B.
Request for information
Answers
B.
Request for information
C.
Statement of work
Answers
C.
Statement of work
D.
Non-disclosure agreement
Answers
D.
Non-disclosure agreement
Suggested answer: B

Explanation:

The statement of work (SOW) would be the next document that a project manager should update once the need to procure goods and/or services is identified. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.