During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
A.
Work with the project scheduler to update the project timeline.
B.
Communicate to the stakeholders about the updated timeline.
C.
Ask the development team to fast-track upcoming activities.
D.
Add two resources so the critical activities will finish on time.