A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

A.
Dashboard
Answers
A.
Dashboard
B.
Gantt chart
Answers
B.
Gantt chart
C.
Work breakdown structure
Answers
C.
Work breakdown structure
D.
Requirements Traceability Matrix
Answers
D.
Requirements Traceability Matrix
Suggested answer: A

Explanation:

A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.