ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 73 - PK0-005 discussion

Report
Export

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.
Critical paths
Answers
A.
Critical paths
B.
Resources
Answers
B.
Resources
C.
Milestones
Answers
C.
Milestones
D.
Work breakdown structures
Answers
D.
Work breakdown structures
Suggested answer: C

Explanation:

Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.

asked 02/10/2024
Tyler Evans
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first