A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

A.
Decline because it is not included in the project scope.
Answers
A.
Decline because it is not included in the project scope.
B.
Assess the impact of the request and create a change request
Answers
B.
Assess the impact of the request and create a change request
C.
Create new functional and non-functional requirements for mobile devices.
Answers
C.
Create new functional and non-functional requirements for mobile devices.
D.
Revise the baseline of the project plan by adding the new requirements.
Answers
D.
Revise the baseline of the project plan by adding the new requirements.
Suggested answer: B

Explanation:

Assess the impact of the request and create a change request. The project manager should assess the impact of the request and create a change request in response to the stakeholder asking to add mobile device functionality to a project that is on track to be completed under budget and ahead of schedule. A change request is a document that formally proposes and records a modification or addition to some aspect of a project, such as scope, schedule, cost, quality, or resources. A change request can help to communicate and justify the need and rationale for the change and its implications on the project objectives and deliverables. A change request also helps to initiate the change control process, which involves reviewing, approving, implementing, and monitoring the change12