Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

A.
Escalate directly to the project sponsor
Answers
A.
Escalate directly to the project sponsor
B.
Push the kickoff meeting out by one week
Answers
B.
Push the kickoff meeting out by one week
C.
Proceed with the kickoff as planned
Answers
C.
Proceed with the kickoff as planned
D.
Identity replacements for project stakeholders
Answers
D.
Identity replacements for project stakeholders
Suggested answer: A

Explanation:

The project sponsor is the person who provides the authority, funding, and support for the project.

The project sponsor can also help to influence and engage the key stakeholders who are essential for the success of the project. If several stakeholders have declined the invitation for the kickoff meeting,

which is an important event to establish the vision, scope, and expectations of the project, the project manager should escalate this issue to the project sponsor and seek their assistance to ensure the participation of the stakeholders1, p. 47