A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.
Project status report
Answers
A.
Project status report
B.
Requirements Traceability Matrix
Answers
B.
Requirements Traceability Matrix
C.
Detect log
Answers
C.
Detect log
D.
Signed project charter
Answers
D.
Signed project charter
E.
Work breakdown structure
Answers
E.
Work breakdown structure
Suggested answer: A