A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

A.
Start-to-finish
Answers
A.
Start-to-finish
B.
Finish-to-finish
Answers
B.
Finish-to-finish
C.
Finish-to-start
Answers
C.
Finish-to-start
D.
Start-to-start
Answers
D.
Start-to-start
Suggested answer: C

Explanation:

A finish-to-start dependency is a type of relationship dependency in project management, where the start of one task depends on the finish of another task12. In this case, the project manager is using a finish-to-start dependency, because testing cannot start until requirements development is finished. This implies that testing is a successor task, and requirements development is a predecessor task.A finish-to-start dependency is the most common type of dependency in project management, and it ensures that tasks are performed in a logical sequence34.Reference= CompTIA Project+ Certification Study Guide5, CompTIA Project+ Certification Exam Objectives6, Understanding Dependencies in Project Management [2023] * Asana1, Dependencies in Project Management | Smartsheet2, Understanding Task Dependencies in Project Management3, What are Dependencies in Project Management?- KnowledgeHut4