List of questions
Related questions
Question 96 - PK0-005 discussion
As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).
A.
Purchase the materials.
B.
Assign the resources.
C.
Accept delays in the work.
D.
Approve the deliverables.
E.
Monitor the performance.
F.
Negotiate with the vendors.
Your answer:
0 comments
Sorted by
Leave a comment first