Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

A.
Creating a backlog
Answers
A.
Creating a backlog
B.
Managing the quality of deliverables
Answers
B.
Managing the quality of deliverables
C.
Updating the issue log
Answers
C.
Updating the issue log
D.
Performing a risk assessment
Answers
D.
Performing a risk assessment
E.
Validating the deliverables
Answers
E.
Validating the deliverables
F.
Reconciling the project budget
Answers
F.
Reconciling the project budget
Suggested answer: E, F

Explanation:

During the project closure phase in the waterfall methodology, it is crucial to validate the deliverables to ensure that all project requirements have been met and the project outputs are complete and satisfactory. Additionally, reconciling the project budget is performed to ensure all financial records are accurate and reflect the actual project costs, which is essential for the formal closing of the project.

Reference= CompTIA Project+ Certification Study Guide (PK0-005)