List of questions
Related questions
Question 112 - PK0-005 discussion
Which of the following can a project manager infer from the following velocity chart?
A.
The project is on schedule.
B.
The project Is ahead of schedule.
C.
The project is behind schedule.
D.
The project is at risk.
Your answer:
0 comments
Sorted by
Leave a comment first