During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.
Pareto chart
Answers
A.
Pareto chart
B.
Milestone chart
Answers
B.
Milestone chart
C.
Burndown chart
Answers
C.
Burndown chart
D.
Gantt chart
Answers
D.
Gantt chart
Suggested answer: C

Explanation:

A burndown chart is a visual representation of the remaining work versus the time required to complete it1.It is commonly used by agile teams to track the progress of each iteration or sprint and to forecast the project completion date2.A burndown chart shows the ideal work remaining line and the actual work remaining line, which can help the team identify any deviations or impediments and adjust accordingly1.A burndown chart is different from a Pareto chart, which shows the frequency of different causes of problems; a milestone chart, which shows the key events and deliverables of a project; and a Gantt chart, which shows the dependencies and durations of tasks in a project3.Reference=CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 6: Planning Projects Part 2, page 173;Burndown Chart: What Is It & How to Use One for Agile - ProjectManager, Introduction and Components of a Burndown Chart sections;Burndown Chart: What it is, How to Use it, Example [2023] * Asana, Introduction and What is a burndown chart? sections.