Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
A.
The project manager did not release the resources.
B.
The project is in the verification testing phase.
C.
The project manager did not complete the project closure phase.
D.
The project manager did not remove access.