Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.
The project manager did not release the resources.
Answers
A.
The project manager did not release the resources.
B.
The project is in the verification testing phase.
Answers
B.
The project is in the verification testing phase.
C.
The project manager did not complete the project closure phase.
Answers
C.
The project manager did not complete the project closure phase.
D.
The project manager did not remove access.
Answers
D.
The project manager did not remove access.
Suggested answer: C

Explanation:

If a project manager continues to receive project-related work after the project has been released into production, it suggests that the project closure phase was not completed properly. The project closure phase involves several activities, including ensuring that all project deliverables are accepted, documenting the lessons learned, releasing project resources, and formally closing the project. If these activities are not completed, the project can remain 'open' in a sense, leading to continued work and inquiries.

Reference= The answer is based on standard project management practices and the importance of the project closure phase as described in project management literature. For detailed information, please refer to the CompTIA Project+ Study Guide and other official CompTIA resources.Specific references to the closure phase can be found in the CompTIA Project+ PK0-005 Cert Guide1and the CompTIA Project+ Certification Exam Objectives2.

asked 02/10/2024
Jonaid Alam
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first