Which of the following is a reason to use a SOW on a project?

A.
To find out the contact information for the vendors
Answers
A.
To find out the contact information for the vendors
B.
To review the list of stakeholders
Answers
B.
To review the list of stakeholders
C.
To ensure the team stays within the scope of the contract
Answers
C.
To ensure the team stays within the scope of the contract
D.
To give explicit instruction on how to execute the work
Answers
D.
To give explicit instruction on how to execute the work
Suggested answer: C

Explanation:

A statement of work (SOW) is a formal document that defines the entire scope of work involved for a vendor and clarifies deliverables, costs, and timeline1.It serves as a contractual agreement between a vendor and a client, providing a comprehensive description of the work to be performed2.A reason to use a SOW on a project is to ensure the team stays within the scope of the contract, as it outlines what the team will and won't do on a project, saving from painful client negotiations and protecting the timeline and the bottom line3.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 3: Initiating Projects Part 1, page 63;What Is a Statement of Work? Definition & Examples, Introduction and What Is a Statement of Work (SOW) In Project Management? sections;Statement Of Work Ultimate Guide: Simple Definition & Template, Introduction and What is a Statement of Work? sections;What Is a Statement of Work (SOW)? - Coursera, Introduction section.