Question 125 - PK0-005 discussion
Which of the following is a reason to use a SOW on a project?
A.
To find out the contact information for the vendors
B.
To review the list of stakeholders
C.
To ensure the team stays within the scope of the contract
D.
To give explicit instruction on how to execute the work