A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?
A.
Gantt chart
B.
Project organization chart
C.
Program Evaluation Review Technique chart
D.
Milestone chart