List of questions
Related questions
Question 150 - PK0-005 discussion
During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?
A.
Escalate the issue with the project sponsor and ask for assistance in managing the situation.
B.
Work with the vendor to achieve a compromise that benefits everyone.
C.
Approve the invoice to avoid damaging the relationship with the vendor.
D.
Schedule a call with the vendor PM and vendor executive to review the statement of work.
Your answer:
0 comments
Sorted by
Leave a comment first