Question 151 - PK0-005 discussion
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
A.
Add a new risk.
B.
Perform an impact analysis.
C.
Escalate to the sponsor.
D.
Raise a change request.