Question 155 - PK0-005 discussion
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
A.
Remove the team member's access.
B.
Release the project resources.
C.
Collect the stakeholders' feedback.
D.
Have the closeout report approved.