Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

A.
Remove the team member's access.
Answers
A.
Remove the team member's access.
B.
Release the project resources.
Answers
B.
Release the project resources.
C.
Collect the stakeholders' feedback.
Answers
C.
Collect the stakeholders' feedback.
D.
Have the closeout report approved.
Answers
D.
Have the closeout report approved.
Suggested answer: B

Explanation:

Releasing the project resources is the process of formally ending the involvement of the project team members and other resources in the project. It also involves updating the resource availability and performance records, and providing feedback and recognition to the resources. Releasing the project resources is an important part of the project closure phase, and it helps to avoid unnecessary costs and conflicts. If the project manager neglects to release the project resources, the team members may still charge time to the project and be unable to work on new projects12.