ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 156 - PK0-005 discussion

Report
Export

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

A.
Remove access.
Answers
A.
Remove access.
B.
Complete the project sign-off.
Answers
B.
Complete the project sign-off.
C.
Release the resources.
Answers
C.
Release the resources.
D.
Outline the lessons learned.
Answers
D.
Outline the lessons learned.
Suggested answer: B

Explanation:

The project sign-off is the formal acceptance of the project deliverables by the client, stakeholder, or customer. It also marks the closure of the project and the release of the final payment. If the project sign-off is not completed, the project may still incur costs and liabilities, which can explain the losses in the financial report. Therefore, the project manager should complete the project sign-off as soon as possible to avoid further losses12.

asked 02/10/2024
Carole Pie
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first