Question 157 - PK0-005 discussion
A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?
A.
SWOT
B.
Risk register
C.
Project schedule
D.
RAC
Your answer: