A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

A.
SWOT
Answers
A.
SWOT
B.
Risk register
Answers
B.
Risk register
C.
Project schedule
Answers
C.
Project schedule
D.
RAC
Answers
D.
RAC
Suggested answer: C

Explanation:

A project schedule is an artifact that shows the sequence, duration, and dependencies of the project activities, as well as the resources assigned to each activity. A project schedule helps the project team understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. A project schedule can also help monitor and control the project progress and performance1.