A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
A.
9 days and $3,000
B.
10 days and $3,200
C.
12 days and $3,800
D.
14 days and $4,000