In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

A.
Developing a RACI
Answers
A.
Developing a RACI
B.
Identifying and assessing stakeholders
Answers
B.
Identifying and assessing stakeholders
C.
Assigning project resources
Answers
C.
Assigning project resources
D.
Establishing communication channels
Answers
D.
Establishing communication channels
Suggested answer: B

Explanation:

Identifying and assessing stakeholders is an action item that will benefit from the analysis of the objectives, the high-level requirements, the success criteria, and the budget resources in the initiation phase. By reviewing these elements, the PM can determine who are the key individuals or groups that have an interest or influence in the project, what are their expectations and needs, and how to engage them effectively throughout the project life cycle12.