In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?
A.
Developing a RACI
B.
Identifying and assessing stakeholders
C.
Assigning project resources
D.
Establishing communication channels