While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?
A.
It highlights the performance issues of the project manager and team members.
B.
It lets the project manager know which stakeholders are allies for future projects.
C.
It helps the project manager create a more structured lessons-learned session.
D.
It identifies the stakeholders' real opinions about the project.