ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 184 - PK0-005 discussion

Report
Export

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

A.
Identify and assess stakeholders.
Answers
A.
Identify and assess stakeholders.
B.
Hold daily status meetings.
Answers
B.
Hold daily status meetings.
C.
Remove access and plan the project sign-off.
Answers
C.
Remove access and plan the project sign-off.
D.
Review assumptions and constraints for input to the risk register.
Answers
D.
Review assumptions and constraints for input to the risk register.
Suggested answer: D

Explanation:

The project manager and team should review assumptions and constraints for input to the risk register during the planning phase of a project. Assumptions are statements that are considered to be true for the purpose of planning, but may or may not be valid in reality. Constraints are factors that limit the project scope, time, cost, quality, or resources. Both assumptions and constraints can introduce risks to the project, which are uncertain events or conditions that can have a positive or negative impact on the project objectives. The risk register is a document that records the identified risks, their causes, impacts, probabilities, responses, owners, and status.Reviewing assumptions and constraints can help the project manager and team identify, analyze, prioritize, and plan for the potential risks that may affect the project12.

The other options are not the correct activities that the team should do during the planning phase of a project. Identifying and assessing stakeholders (option A) is an activity that is done during the initiating phase of a project, not the planning phase.Stakeholders are individuals or groups that have an interest or influence in the project, and their identification and assessment is important to define the project scope, objectives, and success criteria, and to establish a communication plan12. Holding daily status meetings (option B) is an activity that is done during the executing and monitoring and controlling phases of a project, not the planning phase. Daily status meetings are short and frequent meetings where the project team members report on their progress, issues, and plans for the next day.Daily status meetings can help the project manager track the project performance, resolve problems, and communicate updates12. Removing access and planning the project sign-off (option C) is an activity that is done during the closing phase of a project, not the planning phase. Removing access is a security measure to ensure that the project resources do not have access to the project systems, data, or assets after the project is completed.Planning the project sign-off is a process to obtain the formal acceptance and approval of the project deliverables from the stakeholders and customers12.

asked 02/10/2024
Mitesh Patel
44 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first