Which of the following provides the best justification for undertaking a project?

A.
Scope statement
Answers
A.
Scope statement
B.
Business case
Answers
B.
Business case
C.
Sponsor request
Answers
C.
Sponsor request
D.
Project charter
Answers
D.
Project charter
Suggested answer: B

Explanation:

A business case provides justification for undertaking a project, programme or portfolio. It evaluates the benefit, cost and risk of alternative options and provides a rationale for the preferred solution. A business case is essential for demonstrating the value of the project and securing the approval and funding from the governance. A business case is different from a scope statement, which defines the project boundaries and deliverables; a sponsor request, which initiates the project idea and seeks support; and a project charter, which authorizes the project and assigns the project manager. Reference = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 3: Initiating Projects; What is business case? | APM