ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 189 - PK0-005 discussion

Report
Export

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

A.
Performance testing
Answers
A.
Performance testing
B.
User acceptance testing
Answers
B.
User acceptance testing
C.
Stress testing
Answers
C.
Stress testing
D.
Unit testing
Answers
D.
Unit testing
Suggested answer: D

Explanation:

Unit testing is a testing technique that verifies the functionality and quality of individual units or components of software, such as modules, classes, functions, etc. Unit testing can help prevent issues with preexisting capabilities by detecting and fixing errors at an early stage of development, before they affect the integration and system testing. Unit testing can also ensure that new capabilities do not break or interfere with the existing ones, by checking the compatibility and dependencies of the units. Unit testing can be performed by developers using tools and frameworks that automate the process and generate reports. Reference = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 10: Project Quality Management; CompTIA Project+ Certification Exam Objectives, Domain 3: Project Execution, Objective 3.2: Execute quality management activities.

asked 02/10/2024
Bhavani Simhadri
29 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first