List of questions
Related questions
Question 203 - PK0-005 discussion
A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?
A.
Monte Carlo simulation
B.
Root cause analysis
C.
Quantitative risk analysis
D.
Risk response analysis
Your answer:
0 comments
Sorted by
Leave a comment first