A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

A.
Application deployment
Answers
A.
Application deployment
B.
Rollback plans
Answers
B.
Rollback plans
C.
Validation checks
Answers
C.
Validation checks
D.
Maintenance window schedules
Answers
D.
Maintenance window schedules
Suggested answer: A

Explanation:

Application deployment typically involves making a software application available for use, often involving downtime or unavailability of the application. The description of the project manager notifying users about the application being unavailable for a certain period aligns with standard practices during deployment phases. The other options, such as rollback plans, validation checks, and maintenance window schedules, although important, do not directly indicate the action of making an application available for use, as described in the scenario.