Question 204 - PK0-005 discussion
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?
A.
Application deployment
B.
Rollback plans
C.
Validation checks
D.
Maintenance window schedules