A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

A.
Project network diagram
Answers
A.
Project network diagram
B.
Gantt chart
Answers
B.
Gantt chart
C.
Issue log
Answers
C.
Issue log
D.
Risk report
Answers
D.
Risk report
Suggested answer: B

Explanation:

A gantt chart is a visual representation of a project timeline that shows the tasks, durations, dependencies, and resources of a project in a horizontal bar chart format. A gantt chart can help a project manager to calculate the progress of the whole project scope by comparing the planned and actual start and finish dates of each task, as well as the percentage of completion and the critical path. A gantt chart is also a useful tool for communicating the project status and performance to the sponsor and other stakeholders. Therefore, the first document that the project manager should update to calculate the progress of the whole project scope is the gantt chart. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 6: Schedule Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 6: Schedule Management2; What Is a Gantt Chart? 7 Examples for Project Management3