A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

A.
Performing
Answers
A.
Performing
B.
Adjourning
Answers
B.
Adjourning
C.
Forming
Answers
C.
Forming
D.
Norming
Answers
D.
Norming
Suggested answer: D

Explanation:

The current stage of the project team is norming, which is the third stage of the five stages of team development. In this stage, the team members have resolved their conflicts and differences, and have established a sense of cohesion and collaboration. They are more productive, supportive, and cooperative, and they follow the agreed norms and rules of the team. They also communicate effectively and seek feedback and assistance from each other. The norming stage is preceded by the forming stage, where the team members get to know each other and the project goals, and the storming stage, where the team members experience disagreements and challenges. The norming stage is followed by the performing stage, where the team members work efficiently and autonomously towards the project outcomes, and the adjourning stage, where the team members complete the project and celebrate their achievements. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 11: Team Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 11: Team Management2; The 5 Stages of Team Development (Including Examples)3